Concrete Pouring SOP Template

A step-by-step procedure for checking formwork, receiving and placing concrete, finishing the surface and curing it correctly on a construction site.

FreeNo sign-upWord, PDF, Excel & CSV
Ilia PirozhenkoReviewed by Ilia Pirozhenko, Founder, Perfect WikiUpdated September 15, 202612 steps4 roles4 min read
Standard operating procedureSOP-CON-006 ยท Rev 1.0
Owner
Site Supervisor
Effective date
September 15, 2026
Review cycle
Every 12 months

1.Purpose

To make sure concrete is placed, consolidated, finished and cured correctly so the finished structure meets the design strength, tolerance and surface requirements.

2.Scope

Applies to all concrete pours on the construction site, from formwork inspection through placement, finishing and curing, for slabs, footings and structural elements.

Definitions

Slump test
A field test measuring the consistency of fresh concrete to check it matches the ordered mix design before placement.
Segregation
Separation of the coarse aggregate from the cement paste during placement, which weakens the finished concrete.
Curing
Keeping placed concrete moist and at a suitable temperature for a set period so it gains strength properly.

3.Responsibilities

Concrete Crew
Places, consolidates and finishes the concrete, and applies curing measures after finishing.
Site Supervisor
Confirms formwork and reinforcement sign-off, schedules the pour and coordinates the delivery and pump.
Quality Inspector
Inspects formwork and reinforcement before the pour, tests delivered concrete, and verifies curing and stripping timing.
Pump Operator
Positions and operates the concrete pump or chute safely and controls the flow rate during placement.

RACI matrix

ActivityConcrete CrewSite SupervisorQuality InspectorPump Operator
Inspect formwork and reinforcement before pourIAR-
Test delivered concrete on arrivalCIR/AI
Place and consolidate concreteR/AICR
Finish and cure the surfaceR/AIC-
Approve formwork strippingICR/A-

R = Responsible, A = Accountable, C = Consulted, I = Informed

4.Materials and PPE

Materials, tools and systems

  • โ†’Approved concrete mix design and delivery ticket
  • โ†’Slump test cone and testing kit
  • โ†’Concrete pump, chute or bucket
  • โ†’Vibrator for consolidation
  • โ†’Screed board and finishing tools (float, trowel)
  • โ†’Curing compound or curing blankets and plastic sheeting
  • โ†’Formwork and reinforcement inspection checklist

Personal protective equipment

  • โ†’Hard hat
  • โ†’Safety glasses
  • โ†’Rubber boots resistant to wet concrete
  • โ†’Chemical-resistant gloves
  • โ†’High-visibility vest

5.Procedure

  1. 5.1

    Inspect formwork and reinforcement

    Quality Inspector

    Before ordering concrete, the quality inspector checks formwork alignment, bracing and cleanliness, and confirms reinforcement placement, cover and tie-off match the drawings, then signs off the pour.

    Checkpoint: The pour does not start until formwork and reinforcement are signed off against the drawings.

  2. 5.2

    Schedule the concrete delivery

    Site Supervisor

    Confirm the mix design, quantity and pour sequence with the supplier, and schedule the pump or chute and crew to arrive together with the first truck.

  3. 5.3

    Check the delivery ticket and slump on arrival

    Quality Inspector

    On arrival, check the delivery ticket against the ordered mix design and batch time, then perform a slump test and reject the load if it falls outside the accepted range.

    Warning: Never add water on site to adjust slump beyond what the mix design and supplier allow.

  4. 5.4

    Position the pump or chute

    Pump Operator

    Set up the pump line or chute to reach the pour area safely, keeping the discharge point close to its final position to reduce the drop and movement of wet concrete.

  5. 5.5

    Place concrete in sequence

    Concrete Crew

    Place concrete in the planned sequence and in layers, keeping the discharge point close to its final resting place and avoiding dropping or dragging it long distances that could cause segregation.

  6. 5.6

    Consolidate with a vibrator

    Concrete Crew

    Insert the vibrator vertically at regular intervals into each layer, holding it long enough to release trapped air without over-vibrating, and avoid contact with reinforcement or formwork.

  7. 5.7

    Screed and level the surface

    Concrete Crew

    Strike off excess concrete with a screed board guided by the formwork edges or screed rails to bring the surface to the correct level and slope.

  8. 5.8

    Finish the surface

    Concrete Crew

    Float and trowel the surface to the specified finish once bleed water has evaporated, timing the finishing to avoid trapping water or damaging the surface.

    Checkpoint: Finishing starts only after surface bleed water has disappeared.

  9. 5.9

    Apply curing measures

    Concrete Crew

    Apply curing compound, cover with curing blankets, or keep the surface continuously moist as soon as the finish allows, protecting it from rapid drying, wind and temperature extremes.

  10. 5.10

    Maintain curing for the required period

    Site Supervisor

    Keep the curing method in place for the period set by the mix design or project specification, checking coverings periodically to confirm they remain intact.

  11. 5.11

    Approve formwork stripping

    Quality Inspector

    Confirm the concrete has reached the strength required for stripping, based on test cylinder results or the specified time, before authorizing formwork removal.

  12. 5.12

    Clean up and record the pour

    Site Supervisor

    Wash down equipment away from drains in a designated washout area, and record the pour date, quantity, mix design, slump result and any issues in the site log.

6.Quality checks

  • โ†’Formwork and reinforcement are signed off against the drawings before every pour.
  • โ†’Slump test results are recorded for every truck and fall within the accepted range.
  • โ†’Test cylinders are taken and cured for strength testing on structural pours.
  • โ†’Curing measures remain in place for the full period specified for the mix.
  • โ†’Formwork is not stripped before the concrete reaches the required strength.

7.Records

  • โ†’Delivery tickets and slump test results
  • โ†’Formwork and reinforcement inspection sign-off
  • โ†’Test cylinder records and strength results
  • โ†’Pour log with date, quantity and issues noted

8.KPIs

  • โ†’Percentage of loads accepted on first slump test
  • โ†’Number of formwork or reinforcement rejections before pour
  • โ†’Average time between finishing and curing application

9.Common mistakes

  • โ†’Adding water on site to make a stiff load easier to place.
  • โ†’Starting to trowel before bleed water has left the surface.
  • โ†’Skipping curing measures because the crew is in a hurry to move on.
  • โ†’Stripping formwork before test results confirm the concrete has reached strength.

10.Revision history

RevisionDateDescriptionReviewed by
1.0September 15, 2026Initial releaseIlia Pirozhenko

This is a template. Adapt it to your organization, equipment and local regulations before use.

Ask this SOP

Nobody opens a PDF in the middle of a task. They ask.

Add this SOP to Perfect Wiki and your team gets answers in the chat app they already use, with a link to the exact step. Ask from ChatGPT, Claude or Copilot too.

Perfect Wiki AIExample answer

The truck's slump test came back higher than our mix design allows, what do we do?

Reject the load rather than placing it, since concrete outside the accepted slump range can segregate or fail to reach design strength; document the rejection and request a replacement load from the supplier.Source: step 5.3 ยท Check the delivery ticket and slump on arrival
Ask your own question about this SOPโ€ฆSign up to keep asking
Word file vs Perfect Wiki

A downloaded SOP starts going out of date the day you save it.

Screen recorders like Scribe and Tango capture clicks. Perfect Wiki holds the whole procedure, including your recorded guides, and answers questions about it.

Word or PDFPerfect Wiki
Finding itDig through folders and email threadsAsk in Teams, Slack, kChat or Mattermost
Keeping it currentEmail a new version and hopeEdit once with AI, everyone sees the update
Everything in one placeText and imagesEmbed Scribe and Tango guides, SharePoint files and videos
Who can change itAnyone with the fileEditors you choose, everyone else reads
Common questions

Frequently asked questions

Didn't find what you're looking for? Contact our support โ†’

Your SOP library

Keep every SOP where your team can ask it.

Perfect Wiki is the knowledge base for Microsoft Teams, Slack, kChat and Mattermost. Store your SOPs, embed your Scribe and Tango guides, and let AI answer questions with a link to the right step.

No credit cardSetup in under 10 minutesCancel anytime