1.Purpose
To create an accurate, same-day written record of site conditions, manpower, progress, deliveries and issues that project stakeholders can rely on and refer back to.
2.Scope
Applies to daily reporting on all active construction site work, covering every trade and subcontractor working on site that day.
Definitions
- Daily site report
- A same-day written record of weather, manpower, equipment, progress, deliveries and issues on a construction site.
- Delay event
- Any occurrence that stops or slows planned work, such as weather, missing materials or a design query.
3.Responsibilities
- Site Supervisor
- Compiles the daily report from field observations and subcontractor input, and submits it by the end of shift.
- Subcontractor Foreman
- Provides accurate manpower, equipment and progress information for their crew and reviews the report before sign-off.
- Project Manager
- Reviews daily reports for delays and issues, and follows up on items needing client or design input.
- Site Clerk
- Files and archives completed reports and compiles them for weekly progress meetings.
RACI matrix
| Activity | Site Supervisor | Subcontractor Foreman | Project Manager | Site Clerk |
|---|---|---|---|---|
| Record weather and site conditions | R/A | I | I | - |
| Log manpower and equipment on site | A | R | I | - |
| Record progress and delay events | R/A | C | I | - |
| Submit and file the daily report | R | I | A | R |
| Follow up on delay events | R | C | A | I |
R = Responsible, A = Accountable, C = Consulted, I = Informed
4.Materials and PPE
Materials, tools and systems
- โDaily site report form or app
- โSite diary or logbook
- โCamera or phone for site photos
- โWeather reference (thermometer or forecast source)
- โDelivery tickets and material receipts
- โProject schedule for progress comparison
Personal protective equipment
- โHard hat
- โHigh-visibility vest
- โSafety boots
5.Procedure
- 5.1
Record weather and site conditions
Site SupervisorAt the start of the shift, record the weather conditions, temperature and any site condition such as standing water or ground closures that could affect work.
- 5.2
Log manpower on site
Subcontractor ForemanCollect headcount by trade and subcontractor from each foreman, and record it against the crew planned for that day in the daily report.
- 5.3
Log equipment on site
Site SupervisorRecord major equipment present on site that day, such as cranes, excavators and generators, including hours used if tracked for the project.
- 5.4
Log deliveries and materials received
Site SupervisorRecord materials and deliveries received during the shift against delivery tickets, noting the supplier, quantity and any damage or shortage found on arrival.
- 5.5
Record work performed and progress
Site SupervisorDescribe the specific work completed by each trade that day and compare it against the project schedule, noting whether the work is ahead, on track or behind.
Checkpoint: Progress recorded in the report is compared against the current project schedule, not just described in isolation.
- 5.6
Log delays and issues
Site SupervisorRecord any delay event such as weather, missing materials, a design query or access restriction, including the time it started and its estimated impact on the schedule.
Warning: Record delay events the same day, since a late or missing entry can weaken a schedule claim later.
- 5.7
Record safety observations
Site SupervisorNote any safety observation, near miss or incident that occurred during the shift, cross-referencing the separate incident report if one was filed.
- 5.8
Take site photos
Site SupervisorTake dated photos of key progress areas, any delay condition and any damage or defect noted, and attach them to the daily report.
- 5.9
Get subcontractor sign-off
Subcontractor ForemanHave each subcontractor foreman review the manpower, equipment and progress entries for their crew and confirm they are accurate before the report is submitted.
Checkpoint: Every subcontractor foreman confirms their crew's entries before the report is submitted.
- 5.10
Submit the report
Site SupervisorSubmit the completed daily report to the project manager before the end of the site supervisor's shift.
- 5.11
Review and follow up
Project ManagerReview the report for delay events or issues needing client, design or procurement input, and assign follow-up actions with an owner and due date.
- 5.12
File and archive the report
Site ClerkFile the signed daily report and its photos in the project record system so it can be retrieved for schedule reviews or claims.
6.Quality checks
- โA daily report exists for every working day on the project, with no gaps.
- โManpower and equipment entries are confirmed by the relevant subcontractor foreman.
- โDelay events include a start time and estimated schedule impact.
- โReports are submitted the same day rather than backdated later.
7.Records
- โSigned daily site reports
- โSite photos by date
- โDelivery tickets and material receipts
- โDelay event log
8.KPIs
- โPercentage of working days with a same-day daily report filed
- โNumber of delay events logged per month
- โAverage time between shift end and report submission
9.Common mistakes
- โWriting vague progress notes that cannot be compared against the schedule.
- โForgetting to log a delay event until days later.
- โSkipping subcontractor sign-off on manpower and progress entries.
- โNot attaching photos of delay conditions or defects when they occur.
10.Revision history
| Revision | Date | Description | Reviewed by |
|---|---|---|---|
| 1.0 | September 15, 2026 | Initial release | Ilia Pirozhenko |
This is a template. Adapt it to your organization, equipment and local regulations before use.