- Owner
- Maintenance Manager
- Effective date
- September 15, 2026
- Review cycle
- Every 12 months
1.Purpose
To make sure every lubrication point on covered equipment receives the correct lubricant, in the correct quantity, on schedule, to reduce wear and prevent lubrication-related failures.
2.Scope
Applies to scheduled lubrication routes on production and facility equipment, including grease points, oil reservoirs and gearboxes. One-time lubrication performed during a repair or PM task on other equipment is covered by those SOPs.
Definitions
- Lube route
- A defined sequence of lubrication points visited on a schedule, often grouped by area or frequency.
- Lube chart
- The reference showing the correct lubricant type and grade for each point on a piece of equipment.
- Oil analysis
- Laboratory testing of a lubricant sample to check for contamination, wear metals and remaining useful life.
- Re-lubrication interval
- The recommended time or run-hours between applications of grease or oil to a given point.
3.Responsibilities
- Lubrication Technician
- Follows the lube route, applies the correct lubricant and quantity, and records completion and any abnormal findings.
- Maintenance Planner
- Maintains the lube chart and route schedule in the CMMS and orders lubricants.
- Maintenance Supervisor
- Reviews route completion and oil analysis results, and follows up on flagged issues.
- Equipment Operator
- Reports leaks, low oil sight glass levels or unusual noise between scheduled lube visits.
RACI matrix
| Activity | Lubrication Technician | Maintenance Planner | Maintenance Supervisor | Equipment Operator |
|---|---|---|---|---|
| Maintain the lube chart and route schedule | C | R/A | I | - |
| Perform the scheduled lube route | R/A | I | I | I |
| Sample and review oil analysis results | R | C | A | - |
| Report and follow up on abnormal findings | R | I | A | C |
R = Responsible, A = Accountable, C = Consulted, I = Informed
4.Materials and PPE
Materials, tools and systems
- โLube chart for each asset
- โCMMS with the lube route schedule
- โGrease guns and oil transfer containers labeled by lubricant type
- โLubricants specified for each point (grease, gear oil, hydraulic oil)
- โOil sampling kit
- โClean rags and drip pans
Personal protective equipment
- โSafety glasses
- โChemical-resistant gloves
- โCoveralls or apron
- โHearing protection near running equipment
5.Procedure
- 5.1
Review the lube route for the day
Lubrication TechnicianTechnician pulls the day's lube route from the CMMS, noting which points are due and any special instructions from the lube chart.
- 5.2
Verify the correct lubricant grade
Lubrication TechnicianTechnician checks the lube chart for each asset to confirm the correct lubricant type and grade before drawing it from storage, since mixing incompatible lubricants can damage equipment.
Warning: Never mix incompatible lubricant types or substitute a grade not listed on the lube chart.
- 5.3
Inspect lubricant condition and level
Lubrication TechnicianTechnician checks oil sight glasses, reservoir levels and grease fitting condition before servicing, noting any sign of contamination, discoloration or leaking.
- 5.4
Clean fittings before applying lubricant
Lubrication TechnicianTechnician wipes dirt and old grease from each fitting or fill point before connecting the grease gun or opening a reservoir, to avoid introducing contamination.
- 5.5
Apply grease or oil per specification
Lubrication TechnicianTechnician applies the specified lubricant in the quantity and re-lubrication interval called for on the lube chart, avoiding over-greasing bearings.
Checkpoint: Quantity applied matches the lube chart specification for each point, not a generic amount.
- 5.6
Top up oil reservoirs and check filters
Lubrication TechnicianTechnician tops up gearbox and hydraulic reservoirs to the correct level and replaces oil filters that are due per the schedule.
- 5.7
Pull an oil sample where required
Lubrication TechnicianTechnician draws an oil sample from designated points on the schedule using a clean sampling kit and labels it for laboratory analysis.
- 5.8
Clean up spills and dispose of used lubricant
Lubrication TechnicianTechnician wipes up any spilled lubricant, places used oil and rags in the designated waste containers, and disposes of them per the site's environmental procedure.
- 5.9
Inspect for leaks and seal wear
Lubrication TechnicianTechnician checks each serviced point for leaks, worn seals or damaged fittings while completing the route, and notes anything needing follow-up repair.
- 5.10
Record the completed route
Lubrication TechnicianTechnician records completion, quantities applied and any abnormal findings for each point on the lube route in the CMMS.
- 5.11
Review oil analysis results
Maintenance SupervisorMaintenance supervisor reviews returned oil analysis reports for contamination or wear trends and assigns follow-up action if results are outside normal range.
Checkpoint: Oil analysis results outside normal range trigger a follow-up work order before the next scheduled sample.
- 5.12
Update the route and lube chart as needed
Maintenance PlannerMaintenance planner updates the lube route or chart when equipment changes, a lubricant is substituted by the manufacturer, or a repeated leak is found.
6.Quality checks
- โLube routes are completed on schedule at least 95 percent of the time.
- โQuantities applied match the lube chart, with no generic 'grease until full' shortcuts.
- โOil analysis results outside normal range are followed up within the same week.
- โNo lubricant is applied without first checking the lube chart for that point.
7.Records
- โCompleted lube route log in the CMMS
- โLube chart per asset
- โOil analysis reports
- โFollow-up work orders from abnormal findings
8.KPIs
- โLube route completion rate
- โOil analysis samples returned outside normal range
- โBearing and gearbox failures linked to lubrication
- โLubricant consumption against baseline
9.Common mistakes
- โOver-greasing a bearing, which can cause seal failure and overheating.
- โUsing whatever lubricant is closest instead of checking the lube chart.
- โSkipping the leak and seal check because the route is running behind schedule.
- โNot following up on an abnormal oil analysis result.
- โLeaving fittings dirty before connecting the grease gun, pushing contamination into the bearing.
10.Revision history
| Revision | Date | Description | Reviewed by |
|---|---|---|---|
| 1.0 | September 15, 2026 | Initial release | Ilia Pirozhenko |
This is a template. Adapt it to your organization, equipment and local regulations before use.