- Owner
- Production Manager
- Effective date
- September 15, 2026
- Review cycle
- Every 12 months
1.Purpose
To make sure changeovers between jobs are performed safely and quickly, with the correct tooling and settings applied, and the first parts verified before the new job runs at full production.
2.Scope
Applies to changing a machine's tooling, dies, molds or settings to run a different product or job. Starting a line at the beginning of a shift with no product change is covered by a separate SOP.
Definitions
- Setup sheet
- The document specifying the tooling, materials and machine parameters required to run a specific part number.
- External setup
- Preparation work, such as staging tooling, that can be done while the machine is still running the previous job.
- Internal setup
- Setup work that can only be done while the machine is stopped.
- First article
- The first part produced after a changeover, checked against specification before the run continues.
3.Responsibilities
- Setup Technician
- Performs the tooling change and machine parameter setup, and produces trial pieces.
- Production Operator
- Clears previous job material and labels, and runs the machine once the changeover is approved.
- Quality Inspector
- Inspects the first article against specification and approves the run to continue.
- Production Supervisor
- Tracks changeover downtime and releases the line back to the production schedule.
RACI matrix
| Activity | Setup Technician | Production Operator | Quality Inspector | Production Supervisor |
|---|---|---|---|---|
| Stage tooling and materials before line stop | R/A | C | - | I |
| Perform the tooling and parameter changeover | R/A | C | - | I |
| Inspect and approve first article | C | I | R/A | I |
| Track downtime and release the line | I | I | I | R/A |
R = Responsible, A = Accountable, C = Consulted, I = Informed
4.Materials and PPE
Materials, tools and systems
- โSetup sheet for the incoming job
- โTooling, dies or molds for the new job
- โLockout/tagout devices
- โFirst article inspection form and gauges
- โChangeover downtime tracking log
Personal protective equipment
- โSafety glasses
- โCut-resistant gloves for tooling handling
- โSteel-toe boots
- โBack support for heavy tooling moves
5.Procedure
- 5.1
Review the next job's setup sheet
Setup TechnicianSetup technician reviews the setup sheet for the incoming job, confirming the required tooling, materials and machine parameters ahead of the changeover.
- 5.2
Stage tooling and materials before the line stops
Setup TechnicianSetup technician stages the tooling, dies or molds and materials for the next job near the machine while the current job is still running, to minimize downtime.
- 5.3
Shut down and lock out the machine
Setup TechnicianOperator stops the machine using the normal stop, and the setup technician applies lockout/tagout per the site's lockout tagout procedure before removing any tooling.
Warning: Do not remove or install tooling before lockout/tagout is fully applied and verified.
- 5.4
Remove the previous job's tooling
Setup TechnicianSetup technician removes the previous job's dies, molds or fixtures and returns them to their designated storage location.
- 5.5
Install the new tooling
Setup TechnicianSetup technician installs the tooling for the incoming job per the setup sheet, torquing or securing it to the specified values.
- 5.6
Set machine parameters to specification
Setup TechnicianSetup technician removes lockout, restores power, and adjusts machine parameters such as speed, temperature or pressure to the values on the setup sheet.
- 5.7
Run trial pieces
Setup TechnicianSetup technician runs a small number of trial pieces to stabilize the process before calling for first article inspection.
- 5.8
Inspect the first article
Quality InspectorQuality inspector measures a trial piece against the part specification and control plan to confirm the changeover produced a conforming part.
Checkpoint: First article passes every specification characteristic before the job is approved to run.
- 5.9
Adjust settings until parts pass
Setup TechnicianIf the first article fails, the setup technician adjusts parameters and produces another trial piece, repeating until the inspector approves a conforming part.
- 5.10
Clear previous job's WIP and labels
Production OperatorOperator removes any remaining work-in-process, containers and labels from the previous job out of the work area before starting the new job.
- 5.11
Record changeover time and downtime reason
Setup TechnicianSetup technician records the changeover start and end time and the reason for any downtime beyond the target changeover time.
- 5.12
Release the line to production
Production SupervisorProduction supervisor confirms the first article is approved and the area is clear, then releases the line to run the new job at full production.
6.Quality checks
- โFirst article is measured and approved before the job runs past the trial pieces.
- โChangeover time is tracked against the target for the part number and reviewed for outliers.
- โNo previous job's labels or work-in-process remain in the area after changeover.
- โTooling is verified against the setup sheet before installation, not assumed correct.
7.Records
- โSetup sheets by part number
- โFirst article inspection forms
- โChangeover downtime log
- โTooling storage and maintenance log
8.KPIs
- โAverage changeover time by part number
- โFirst article pass rate on the first trial piece
- โChangeover-related downtime as a percentage of scheduled time
- โNumber of changeovers requiring more than two trial adjustments
9.Common mistakes
- โStarting internal setup work before staging tooling externally, adding unnecessary downtime.
- โSkipping lockout/tagout for what seems like a quick tooling swap.
- โEyeballing the first article instead of measuring it against the specification.
- โLeaving old job labels or containers in the area, risking mixed product.
- โNot recording the actual changeover time, so slow changeovers go unnoticed.
10.Revision history
| Revision | Date | Description | Reviewed by |
|---|---|---|---|
| 1.0 | September 15, 2026 | Initial release | Ilia Pirozhenko |
This is a template. Adapt it to your organization, equipment and local regulations before use.