- Owner
- Procurement Manager
- Effective date
- September 15, 2026
- Review cycle
- Every 12 months
1.Purpose
To issue accurate, properly authorized purchase orders to suppliers and track them through delivery and invoice matching, so the business pays only for what was ordered and received.
2.Scope
Applies to creating, issuing, amending and closing purchase orders once a requisition is approved. Requisition approval and supplier selection are covered by separate SOPs.
Definitions
- PO
- Purchase Order, the formal document sent to a supplier authorizing a purchase at agreed price and terms.
- Three-way match
- Comparing the purchase order, the receiving record and the supplier invoice before an invoice is approved for payment.
- Open PO
- A purchase order that has been issued but not yet fully received or closed.
- PO amendment
- A formal change to an issued purchase order, such as a quantity, price or delivery date update, requiring reapproval.
3.Responsibilities
- Procurement Analyst
- Creates and issues purchase orders, tracks open orders, and coordinates amendments with suppliers.
- Procurement Manager
- Approves purchase orders above the analyst's authority and resolves supplier delivery disputes.
- Receiving Clerk
- Confirms goods receipt against the purchase order quantity and condition.
- Accounts Payable Clerk
- Performs the three-way match and approves the supplier invoice for payment.
RACI matrix
| Activity | Procurement Analyst | Procurement Manager | Receiving Clerk | Accounts Payable Clerk |
|---|---|---|---|---|
| Create purchase order from requisition | R/A | A | - | - |
| Issue PO to supplier | R/A | I | - | - |
| Track open PO status | R/A | I | C | - |
| Confirm goods receipt | I | - | R/A | I |
| Perform three-way match and approve invoice | C | I | C | R/A |
R = Responsible, A = Accountable, C = Consulted, I = Informed
4.Materials and PPE
Materials, tools and systems
- โERP or procurement system PO module
- โApproved requisition records
- โSupplier contact and terms reference
- โPO amendment request form
- โThree-way match checklist
- โOpen PO tracking report
5.Procedure
- 5.1
Confirm the requisition is approved
Procurement AnalystVerify the requisition has completed all required approvals before creating a purchase order against it, and do not create a PO from an unapproved or partially approved requisition.
- 5.2
Select the supplier and confirm terms
Procurement AnalystSelect the supplier from the approved catalog or the outcome of a completed sourcing process, and confirm current pricing, lead time and payment terms before drafting the PO.
- 5.3
Draft the purchase order
Procurement AnalystDraft the PO with item description, quantity, unit price, delivery address, requested delivery date and payment terms, referencing the original requisition number.
Checkpoint: Every PO references its originating requisition number and matches its approved cost and quantity.
- 5.4
Approve the purchase order
Procurement ManagerRoute the draft PO for approval per the authority matrix, escalating to the procurement manager if the value exceeds the analyst's threshold.
- 5.5
Issue the PO to the supplier
Procurement AnalystSend the approved PO to the supplier through the agreed channel, whether EDI, email or a supplier portal, and confirm the supplier has acknowledged receipt.
- 5.6
Confirm supplier acceptance
Procurement AnalystObtain the supplier's confirmation of the order, quantity, price and promised delivery date, and follow up if acknowledgment is not received within a set number of business days.
Warning: Do not assume a PO is accepted just because it was sent; an unconfirmed order can lead to a missed delivery with no recourse.
- 5.7
Track the open PO
Procurement AnalystMonitor the open PO against its promised delivery date, following up with the supplier proactively if the date is approaching without a shipment confirmation.
- 5.8
Process a PO amendment
Procurement AnalystFor a change in quantity, price or delivery date after issuance, document the amendment request, obtain supplier agreement, and reapprove the updated PO before it takes effect.
- 5.9
Confirm goods receipt
Receiving ClerkConfirm the receiving team recorded the goods receipt against the correct PO number, noting any quantity or condition discrepancy from what was ordered.
Checkpoint: Receipt quantity and condition are recorded against the PO number before the PO can be closed.
- 5.10
Resolve a receiving discrepancy
Procurement AnalystFor a shortage, overage or damaged delivery against the PO, work with the supplier to resolve it through a credit, replacement shipment or partial PO closure.
- 5.11
Perform the three-way match
Accounts Payable ClerkCompare the purchase order, the goods receipt record and the supplier invoice, confirming quantity and price match before approving the invoice for payment.
- 5.12
Close the purchase order
Procurement AnalystOnce fully received and invoice-matched, close the PO in the system, and archive it with its requisition, receipt and invoice records for audit purposes.
6.Quality checks
- โNo purchase order is created from an unapproved requisition.
- โEvery PO references its originating requisition and matches its approved value.
- โSupplier acceptance is confirmed for every issued PO, not assumed.
- โInvoices are approved for payment only after a completed three-way match.
7.Records
- โIssued purchase orders
- โSupplier acceptance confirmations
- โPO amendment requests and approvals
- โThree-way match and closure records
8.KPIs
- โPercentage of POs issued within a set time of requisition approval
- โOn-time delivery rate against promised PO date
- โPercentage of invoices matching on first three-way match attempt
- โAverage days to close a fully received PO
9.Common mistakes
- โCreating a purchase order before the requisition is fully approved.
- โAssuming a supplier accepted a PO without confirming it.
- โLeaving a PO open long after goods were received and invoiced.
- โApproving an invoice for payment without completing the three-way match.
10.Revision history
| Revision | Date | Description | Reviewed by |
|---|---|---|---|
| 1.0 | September 15, 2026 | Initial release | Ilia Pirozhenko |